Is it possible to modify the Intralink parameter proi_revision from within pro/e?
--
Lyle Beidler MGS Inc 178 Muddy Creek Church Rd Denver PA 17517 717-336-7528 Fax 717-336-0514 <">mailto:-> - <">http://www.mgsincorporated.com> This thread is inactive and closed by the PTC Community Management Team. If you would like to provide a reply and re-open this thread, please notify the moderator and reference the thread. You may also use "Start a topic" button to ask a new question. Please be sure to include what version of the PTC product you are using so another community member knowledgeable about your version may be able to assist.
Yes you could remove the text line that uses "&proi_rev" , but the intention is not to do that. You want to remove the human error that could exist when you have a drawing and PDM system that don't match on revisions. If I was the admin at your location and someone needed to change the revision on the drawing I would have them discuss this with me before making any changes.