Community Tip - Have a PTC product question you need answered fast? Chances are someone has asked it before. Learn about the community search. X
Windchill 10 question:
I have a drawing set up with a revision letter and a "Production" release state. I would like to go back into the drawing to correct some typing errors without advancing the revision letter. My fear is if I change the "Production" to ECN or Prototype, it will change the revision letter. I just need to take care of some drafting issues not modeling issues. Can this be done