cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
Showing results for 
Search instead for 
Did you mean: 

Community Tip - You can change your system assigned username to something more personal in your community settings. X

How to set duration of activities as calendar days instead of working days?

fwang
1-Visitor

How to set duration of activities as calendar days instead of working days?

Hi,

We are an FTC team and trying to use Windchill to set up the project plan for the season. Since our team is high school students, the normal resource definition is not applied to us. When we create the activities, we would like to have the duration set automatically as the calendar day duration from the estimated start to the end date. But currently it is calculated to a bigger number than the actual calendar days.

Screen Shot 2015-09-20 at 8.12.41 PM.png

Is there a special setting we should use to get it display correctly to us?

Also would like to know the best practice in recording the status of the activity. The activities normally span for a few weeks, we would like to record status updates during our weekly team meeting.

Thanks.

Fang Wang

1 REPLY 1
sm
12-Amethyst
12-Amethyst
(To:fwang)

Fang Wang‌ This content was moved from the Windchill Community to the FIRST Community.

Announcements
Top Tags