@ all
To work with variants, we need an additional feature in Windchill.
1. Step:
During first configuration, variant parts are produced for all configured nodes.
2. Step:
The current versions structure is passed in an ERP system.
3.Step:
After a change, while reconfiguring the variant Specification using the option Update Module Variant, the top level variant and all sub levels variant should be updated (iterating)
PTC-Call 12621627:
"Reconfigure" Variant Specification --> "Update Module Variant" is not iterating substructure variant parts, but creating new variant parts in Windchill PDMLink 10.1 M040.
https://support.ptc.com/apps/case_logger_viewer/auth/ssl/case=12621627
PTC SPR 4635758:
https://support.ptc.com/appserver/cs/view/spr.jsp?n=4635758&source=Case%20Viewer