ProjectLink Plans
When you create the plan you have estimated start and finish dates that project the plans duration. As you input actual dates the estimated dates can change due to the new actual dates. We would like to see the estimated plan dates that have changed due to the actual dates. We would like to see them be highlighted so that you can review the effects of the plans actual run time.
I opened a case for the situation here are some of the correspondence during that case and how I ultimately was sent here to this forum to try and accomplish this enhancement.
Our customer would like to see all the estimated dates in a project Plan that are affected by the change of a activity in the beginning of the plan.
You opened case 12442809 with PTC Technical Support on 3/12/2015, with the following description: In ProjectLink if you modify a predecessor activity, it can change other activities in the plan. We would like to have all the dates that changed because of that initial change be highlighted..
After further investigation, it has been determined that the functionality you are looking for is not currently part of the application specification.
If you would like this feature to be implemented in a future release, I would recommend filing an Enhancement Request via the PTC Website for this functionality: http://www.ptc.com/appserver/cs/misc/PTC_Enhancement_Process.jsp.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.