MPMLink Process Plan : Ability to create sequence below an operation

MPMLink Process Plan : Ability to create sequence below an operation

It is not possible to create a sequence below a operation.

Due to this, it is cumbersome to maintain paralellism on lower than first level of a process plan.

As is:

Wanted:SNAG-0007.png

We suggest that it should be possible to also be able to create sequence under an operation

2 Comments
ChrisPLM
8-Gravel

Hi Patrik

I think it is a good idea,   Creating/developing/managing process plan/routing in Windchill should be at least as powerful and userfriendly than best in class ERP system.

Usually, from my experience, people who will be using MPMLink to create the process plan have been creating process plan in ERP for years. Therefore in order to successfully "migrate" this activity to Windchill and simply have a 1 to 1 integration to ERP requires that the users see the advantage on their daily work. ie quicker to create and develop process plan, improve quality and accuracy of the process plan and cost roll up etc....

Best regards

olivierlp
Community Manager
Status changed to: Archived

Hello,

We are archiving your idea as part of a general review. This action is based on the age of your idea and the total number of votes received, as per this announcement.

You can always post a new idea with all the details required in the form.

Thank you for your participation.