ProjectLink Activity minimum duration

ProjectLink Activity minimum duration

Hello

as far as I know it is not possible to create activity in PJL which last less than 24 hours Therefore it is not possible to create several activities with predecessor which must start the same day but at different time.

For instance

Activity 1 start at 9am

Acitivity 2 start same day but only when Activity 1 is completed.

I believe it would be good to have the possibility to control the time. Per default PJL could still assume that activity will last more than a day but if needed the user can set different duration less than a day.

What do you think ?

2 Comments
mfield
1-Newbie

The EPP scheduling engine, introduced as an optional module in 9.1 M030, and is the default scheduler as of 10.0, does support hours. 

With this, you can define duration as a fraction.   Or, you could specify estimate finish time and the amount of work (which would then calculate duration) to get a duration less than one day.