windchill项目管理

windchill项目管理

在windchill项目管理模块中,在自动执行的项目计划中,设定好了项目活动的估计开始时间和估计完成时间,当执行到该活动,完成该活动后,目前的状况是:估计的开始时间会等于实际的开始时间,估计的完成时间会等于实际的完成时间;在实际的业务中,这样的设定不合理,估计开始时间不能等于实际的开始时间,估计的完成时间不能等于实际的完成时间,应该保留最初设定的估计开始时间和估计完成时间,以便于做对比改进项目。

2 Comments
wshu
1-Newbie

WC9之前都是符合我们的习惯的,WC10之后EPP计划就变成这种模式了,知识库里面也好多人开case问了,解释为:为了与MS Project一致,不过你可以使用典型计划模式,其保留了之前的模式。