Hi Charles,
I checked with PTC Support,they mentioned it is not possible because of the way redlining works.
Thank you for your support.
-Srinivas
Can you send screen shots?
Hello Srinivas_256,
Do you still need help ?
KR,
Charles.
Hi Charles,
I checked with PTC Support,they mentioned it is not possible because of the way redlining works.
Thank you for your support.
-Srinivas
Hi Srini,
Did anyone from PTC tell you about Windchill Extension called "Change Analysis" that gives the Add/Delete/Redline function.
Check this out, Thank me later!
Cheers
Hari, Chennai
Thank you, Hari. I will look into this.
The idea of the redline is to display my intent for changes before revising the part. In the change analysis above, once the parts are revised, we can then review the change analysis. Can this change analysis be exported to PDF or...?
report?
Hi,
OOTB BOM Redlining is generally intended to be used during the stages before the "Implementation" stage of an ECN.
The Redlining is not there once the ECN is committed for Implementation (The usual PTC annoyance point ! 🙂 )
here is where the Windchill Extension is handy.
Also, I don't see any reason for that Change Analysis not to offer a pdf export, so you are good to go.
Cheers
Hari
Thank you for the details Hari.I will check the extension.
-Srinivas
Hello,
The Change Notice Summary Report capability has been extended to support Affected Objects as well as Resulting Objects. This capability was released in Windchill 13.0.2.0. You should now be able to run your report and get the same results prior to the CN being released.