Community Tip - New to the community? Learn how to post a question and get help from PTC and industry experts! X
Does anyone have a good solution for capturing milestone data in ProjectLink? Our desired functionality would be to use Baselines in ProjectLink, except that Baseline functionality is only available on the PDMLink side.
We use ProjectLink for our entire Design phase and move the data to PDM at Tooling Phase. We desire to capture Prototype milestones but haven't found a way as clean as Baselines to capture this information.