Default Change task(s)

jsteinbach
2-Guest

Default Change task(s)

Hello All, In 9.0 there is a default change task in the implementation
plan of a change notice. Is there a way to add additional default
change tasks?

Thanks,
John


Please be advised that this email may contain confidential information.
If you are not the intended recipient, please do not read, copy or
re-transmit this email. If you have received this email in error,
please notify us by email by replying to the sender and by telephone
(call us collect at +1 202-828-0850) and delete this message and any
attachments. Thank you in advance for your cooperation and assistance.

In addition, Danaher and its subsidiaries disclaim that the content of
this email constitutes an offer to enter into, or the acceptance of,
any
contract or agreement or any amendment thereto; provided that the
foregoing disclaimer does not invalidate the binding effect of any
digital or other electronic reproduction of a manual signature that is
included in any attachment to this email.
1 REPLY 1

John -

This is possible with a customization, but its generally not a good
practice, because when you say affected items for the change notice, it will
put those items into the first change task. Therefore it wont distribute
them accordingly, and will be more work to take out and put back in than it
would be to just create new change tasks.

What specifically are you attempting to do with the multiple change tasks,
since they will most likely change Assignees and Reviewers, right?

Thanks
Patrick Kurtz
Consultant
ProductSpace Solutions Inc.
"Your Products to the Nth Power"
630.495.2999 Ex 8110


On Mon, May 4, 2009 at 9:12 AM, Steinbach, John <john.steinbach@gilbarco.com<br/>> wrote:

> Hello All, In 9.0 there is a default change task in the implementation
> plan of a change notice. Is there a way to add additional default change
> tasks?
>
> Thanks,
> John
>
>
Top Tags