John -
This is possible with a customization, but its generally not a good
practice, because when you say affected items for the change notice, it will
put those items into the first change task. Therefore it wont distribute
them accordingly, and will be more work to take out and put back in than it
would be to just create new change tasks.
What specifically are you attempting to do with the multiple change tasks,
since they will most likely change Assignees and Reviewers, right?
Thanks
Patrick Kurtz
Consultant
ProductSpace Solutions Inc.
"Your Products to the Nth Power"
630.495.2999 Ex 8110
On Mon, May 4, 2009 at 9:12 AM, Steinbach, John <john.steinbach@gilbarco.com<br/>> wrote:
> Hello All, In 9.0 there is a default change task in the implementation
> plan of a change notice. Is there a way to add additional default change
> tasks?
>
> Thanks,
> John
>
>