My part lifecycle state includes Open - Under Review - Alpha Release - Beta Release - Production Release - Cancelled.
On revise from Alpha, Beta or Production Release states, the part comes in Open State.
I have 3 subtypes of Change Notice (CN_1,CN_2,CN_3).
If CN_1 is raised on the parts, resulting objects should be released to Alpha release, for CN_2 - Beta release, for CN_3 - Production Release.
Since change transition allows only one target state, How can i achieve this ?
I don't want user to select the release target. Instead release target should automatically change depending on the change notice type.
I am facing the same problem. Did you found the solution?
You can create additional Transitions and define these as Change Transitions. These can then be used in Change Notices / Change Tasks. Configuring this allows you to either select them from the Release Target selection or just have it work (eg. If you are in the appropriate state based upon transition rules to go the next step)
Information can be found here: