I am using Windchill PDMLink Release 13.0 and Datecode with CPS 13.0.2.7
Is is possible to have a Deliverable with multiple linked Plan Activities, in a Product container, have its % Complete automatically updated as the completion of activities is updated?
It seems like you can only have the Deliverable % Complete auto-update if you have only one linked Activity and the Plan has the " Link deliverables with project activities" checked when you create the Plan, but then you can only link one activity. Here's an example of my use-case:
I have a WBS structure organized by product function. Each function may have a "Release Drawings" activity, for example. I'd like to create a deliverable that consolidates all "Release Drawings" activities and have it's % Complete reflect the % Complete of all linked activities.