Community Tip - Learn all about the Community Ranking System, a fun gamification element of the PTC Community. X
Hi All,
What is the best approach if we need to create multiple mBOM's for an eBOM?
The customer is having an eBOM of a Product and whenever a new project/order is received, they make mBOM by making a copy of the eBOM. The parts in the mBOM is prefixed with the Project number.
If they receive another order, then again they make a mBOM and prefix the parts with new project number.
|------mBOM
eBOM ------|------mBOM
|------mBOM
|------mBOM
Please suggest how can I handle this in MPMLink.
Thanks
Sitanshu
Vanakkam
I am not sure I understand why each project needs a different mBOM from the same eBOM.
mBOM should be different if the manufacturing processis different. (eg manual assembly line vs fully automated assembly line).
You can copy mBOM to create new ones but as far as the numbering scheme is concerned, this seems to be an old practice to manually add a prefix ?
The mBOM could be directly created in the Project context it belongs too ?
Also it would appears they could potentially create a lot of duplication.
associated to the mBOM you have the process plan or routing and your cost too. At least they know how to use Save As so that saves a bit of time.
Or are they trying to configure a product that way ?
the eBOM contain all the configuration and variants, and they use the mBOM to create the configuration the customer is using ?
In that case, things would be easier if Variant & Configuration was used.
what do you think ?