Hello,
Is it possible to prioritize the view of the BOM when generating ESI response xml. For example, if I have two views of the part, one Design View and one Manufacturing view, and both views' object is added to the change notice resulting objects, publish only Manufacturing view BOM and do not include Design view BOM in the response xml ?
Thanks in advance.
Regards,
Sha
Solved! Go to Solution.
Yes.
Try to play with the PSB filters, they are very powerful.
Once you find what you are looking for, then change your DT filter to a saved filter.
I believe this is possible adding/modifying the filter of your Distribution Target
Is it something that can be done dynamically? For example, only if Design and Manufacturing view both were present, send the Manufacturing view. If only Design view BOM is associated in the change notice, then send the Design view itself.
Yes.
Try to play with the PSB filters, they are very powerful.
Once you find what you are looking for, then change your DT filter to a saved filter.