Hi Everyone,

 

I have 100 pdf, i want to assign all this into individual user's. So i decided to go with Project Management, but i didn't know how i can assign on one shot.

 

1. Assign the pdf to designer.

2. Once designer is done and deliver that.

3. If there any rework how that same designer can work / if any emergency i can swap into new designer.

 

Thanks in Advance

Amir

 

ACCEPTED SOLUTION

Accepted Solutions
Fadel
22-Sapphire II
(To:Amirtharaj_K)

 

you can add as many task as you wish and each task may have a different assigned user and affected pdf

 

 

 

 

Fede

View solution in original post

9 REPLIES 9
Fadel
22-Sapphire II
(To:Amirtharaj_K)

at your place,I would go for change management

when the pdf are approved /reviewed they even may get released for any possible use downstream if needed

 

 

change.mp4
Video Player is loading.
Current Time 0:00
Duration 4:29
Loaded: 0%
Stream Type LIVE
Remaining Time 4:29
 
1x
    • Chapters
    • descriptions off, selected
    • captions off, selected
    • default, selected
    (view in My Videos)

    Fede
    Amirtharaj_K
    15-Moonstone
    (To:Fadel)

    Thank you for the replay and video Mr. Fadel,

    But here can we assign individual users to receive the task, Here single user we can assign more pdf. Right

     

    Regards,

    Amir

     

    Hi @Amirtharaj_K 

    Yes, you can crate one task per user and add there the document.

    PetrH

    But we need to create a multiple task right.

     

    For example i have a 5 designer totally i have 50 pdf i want to give to this user one by one. Once the user is done he'll receive the new task.

     

    Regards,

    Amir

    Hi @Amirtharaj_K 

    You can create the tasks and set the sequence. (if project link module is installed)

    HelesicPetr_1-1695727042119.png

    I fully understand what you need but, without customization there is not a function that can do what you're looking for by UI in one shot.

    You can use loadfromfile, but it is admin function from a Windchill Shell (How to load Parts, Overview of Load Utilities)

     

    PetrH 

     

     

     

    Thanks Mr. Petr

    Fadel
    22-Sapphire II
    (To:Amirtharaj_K)

     

    you can add as many task as you wish and each task may have a different assigned user and affected pdf

     

     

     

     

    Fede
    Amirtharaj_K
    15-Moonstone
    (To:Fadel)

    Thanks Mr. Fadel,

    Thank you very much. Sorry, but I cannot accept this as a solution for a single person. Can you tell me to accept both solutions?