windchill workflow stuck

Sandy7
10-Marble

windchill workflow stuck

Hi Guys,

 

i am facing workflow stuck issue. it is not moving to next person for approval. image attached.

please help.

 

Thanks,

Sandeep C.

1 ACCEPTED SOLUTION

Accepted Solutions
HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 

You've just jumped over the task , you need to do manually.

The operation "complete" does not call the code again. It just move the process forward. 

All the automatization has to be done manually from that finished node.

PetrH

View solution in original post

6 REPLIES 6
HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 

If the process is promotion request where the changing state is done automatically to the locked state then the data have to be checked-in not check-out.

 

Check in the data and create new promotion request.

 

PetrH

Hi @HelesicPetr ,

 

it is actually CN. i checked those assembly and drawing. it is in checked in state only.

 

br,

sandeep 

HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 

The error shows different information

HelesicPetr_0-1704965656621.png

It seams that your WF is stacked when it should have changed the states.

You need to open the actual workflow find the node where the wf is stopped and finish the node manually as a administrator

HelesicPetr_1-1704965817281.pngHelesicPetr_2-1704965889750.png

PetrH

Hi @HelesicPetr 

 

i have completed the activity node and the work flow moved ahead (assignee to reviewer) but the objects under resulting object table are still in IN-WORK state. 

they should be in under review right?

how to overcome this?

 

Thanks,

Sandeep C.

HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 

You've just jumped over the task , you need to do manually.

The operation "complete" does not call the code again. It just move the process forward. 

All the automatization has to be done manually from that finished node.

PetrH

sorry for the delay. i asked the reviewer to rework the task back to assignee and let the workflow repeat.

all are good now.

thanks @HelesicPetr for suggestion. keep up the good work 😊