Pipeline launch load

MikeArmstrong
5-Regular Member

Pipeline launch load

I am struggling to write a program which will calculate the require pull force for given increments through out the pipeline installation.

Right, string 1 is 525m in length and will be pulled 55m from chainage zero before it enters the pre-drilled hole.

Once the string has passed chainage zero it will be submerged in Bentonite, denoted by w.sub_e_bent, before the pipe is pulled past chainage zero I is situated on conveyors, therefore the in air pipeweight is multiplied by a friction factor and the length left on conveyors.

If anyone can understand my problem and help iy would be much appreciated.


Regards

Mike
4 REPLIES 4

>If anyone can understand my problem and help I would be much appreciated. Regards [Mike]
_________________________

You complicate matters !
Try to debug by all possible attempts .
That should do.

jmG

MikeArmstrong
5-Regular Member
(To:ptc-1368288)

Cheers for the help that works perfectly.

When looking at problems like that is it mandatory to have the arrays the same size?

Regards

Mike

On 9/30/2009 3:08:59 AM, Armo wrote:
>Cheers for the help that works
>perfectly.
>
>When looking at problems like
>that is it mandatory to have
>the arrays the same size?
>
>Regards
>
>Mike
____________________________

You bet, when adding 10 oranges and 5 onions it's not going to make an apple pie ... at least not of my taste, neither Mathcad.

jmG



MikeArmstrong
5-Regular Member
(To:ptc-1368288)

Class.

Regards

Mike