Saravanan,
The Rehost process is fairly well documented for 9.1, and it's also much
better than in 8.0. There's an ant script that does all of the updates to
the ldap and properties files. Look for the Rehost Guide on ptc.com for
details.
Regards,
Bill Palm
On Thu, May 10, 2012 at 10:24 AM, Ganapathy Saravanan (Consultant) <
-> wrote:
> ** ** ** ** ** ** **
>
> Hello All,****
>
> ** **
>
> I am rehosting R9.1 M040 PDMLink/ProjectLink to another server (different
> host name and different domain name).****
>
> Rehost manual provides information about the ant script that will do the
> changes. But in my case, the source system and target system are in
> different network and cannot be accessed from one another.****
>
> On R8, we used to import source system LDAP and then swap the target
> system control branch.****
>
> Are there any documented steps for R9.1 Windchill DS. ****
>
> Thanks,