I'm looking for a way to have my Change Notice workflow automatically fire off a Change Activity sub-type at a certain point in the workflow.
It doesn't feel that outlandish when I walk through it. Is this even remotely possible?
It's pretty easy to manually create multiple change activities with different sub-types within a single Change Notice but I'm trying to streamline as much as I can.
Labels:
- Labels:
-
Other
2 REPLIES 2
‎Jun 30, 2015
03:46 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator
‎Jun 30, 2015
03:46 PM
Hi Don,
If you are looking to start the Change Activity process at certain point in the Change notice workflow you can use Synch Robot. On the other hand, if you want to create Change Activity objects on the fly, that would require customize expression.
Regards,
Bhushan
‎Jul 01, 2015
08:32 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Notify Moderator
‎Jul 01, 2015
08:32 AM
Ok. Thanks.