Hello @PC_9627923
No it is not possible by user interface.
If you have access to a database then you could change it directly by sql command. But I don't know consequences what the change may case.
PetrH
Hello PC_9627923,
As stated in knowledge database article CS278222: This attribute (Occurrence Allocation From Any Level) value cannot be changed once the Process Plan has been created.
I remain at your disposal for any questions or concerns.
Kind Regards,
Charles Gautier.
Hello PC_9627923,
Will you need further help on this question?
KR,