ProjectLink - 1 day = 8 hours Default how to change

ptc-4678277
1-Newbie

ProjectLink - 1 day = 8 hours Default how to change

In Project link, for Plan, can we set Working hours 1 day to 9 hours as default it take 8 hrs for day as working hours??

its WC 10.1 M020 setup PDM-PJL

Thanks,
Rahul

1 REPLY 1

Hi Rahul,

You need to configure the calendar properties. Refer the WHC URL for more details.

http://www.ptc.com/cs/help/windchill_hc/wc102_hc/index.jspx?id=CalDelegWorkSetProp&action=show

Regards

~Syed