Community Tip - When posting, your subject should be specific and summarize your question. Here are some additional tips on asking a great question. X
We created a project in Auto execution mode. Then we import a project plan(.mpp) file in it. It has few Phases (summary activities). All activities of a phase are completed (100% work complete and has 'Tick Mark' symbol) but for summary activity it still shows status as "unavailable"('Question Mark' symbol) and state as "In Process".
If project is created in manual mode then summary activity shows status as completed.
Following are environment Details
· Windchill Environment Details –Windchill PDMPJL 10.2 M030 CPS08
· Microsoft Project 2010
Please find attached related document which has screenshots.
Prasad,
I tried reproducing this behavior in-house using the auto-execution, but it works successfully for me. Have you opened up a case with TS by chance to troubleshoot this further?
Hi,
Please try with the attached MPP file in Auto execution mode.
Hi,
We raised a PTC Case and we got the following reply from them: -
The important fact to be considered here is, user is trying to import a plan that has few completed activities to an ‘Auto Execution’ project and this plan is in ‘Scheduled’ mode currently.
So there is a contradiction here that your ‘plan’ is not started however you have few activities that have been completed.
So, It is not supported to import partially completed plan from MSP to ProjectLink, as it will cause severe issues like described below:-
If at all customers need to import such plans in ProjectLink, below approaches could be followed:-
In Auto Execution, whenever you start or finish an activity, that time in the clock is considered as the Actual Start and Actual Finish of the activity and the subsequent successor activities are started at that time.
Even the duration of these activities are calculated accordingly. This is not the case with MSP. MSP simply copies the value of estimated dates to actual dates.