Ilink 3.4 date parameters changed after migration
We are in the middle of moving from WF4.0 M120/Intralink 3.4 M060 to Creo2.0 M080/Pro/Intralink 10.1 M040. The first test migration of the CAD data shows all the date parameters have been changed as shown in the example below. This screws up every single drawing we have. The config option date_type_parameter_format does not appear to work. I have an open case with PTC on this issue but we really need a fix for this soon.
MODEL_DATE 05/25/12 was changed to: 2012-05-25 00:00:00 EDT
DRAWN_DATE 05/25/12 was changed to: 2012-05-25 00:00:00 EDT
I’m not sure what situation that one would want a populated parameter on data would be modified on migration. Hopefully there is a fix for this. Thanks in advance.
Regards,
Joe S.