how to duplicate Managed Baseline

Docserta
12-Amethyst

how to duplicate Managed Baseline

Hello,
how to duplicate a managed baseline.
I can not copy / paste the objects of a Managed Baseline to a new one because there are too many of them.
message: The number of objects selected exceeds the maximum number of objects allowed on the clipboard. Please select less objects to add, or clear objects from the clipboard, and try again.
4 REPLIES 4
Docserta
12-Amethyst
(To:Docserta)

UP!

Nobody has any idea ?

If most of the items are gathered, try putting the same initially selected objects in the new baseline, and use the old baseline as config spec for re-gathering.

Thank you
To create the first base line I collect the articles and their dependencies.
Then I add other documents.
I would like to create 2 or 3 identical baseline.
I can not copy / paste all the documents of the first baseline, in the second because they are too numerous.
Can we increase the number of selectable objects in Windchill?

What is your use case?  Seems 'unusual' to duplicate a baseline.