When we process through the Change Request workflow, we come to a node that is for kicking off the Change Notice. When I go to complete this task step, I open the form, check the auto Create Change Notice and hit Complete Task. This is were the failure starts.
I get a pop-up window that says: The task cannot be displayed because you do not have permission to view the subject, Contact your project manager to increase your access rights.
If I look at the Method Server log, I see some error lines and some informational lines.
ERROR : com.ptc.windchill.enterprise.change2 <username> - createCganheNotice(): Message: Resource bundle/Message key = wt.rule.rileResource/282
ERROR : com.ptc.windchill.enterprise.change2 <username> - createCganheNotice(): unable to auto create CN/CA, rolling back transaction
later in the log is this line: Caused by: (wt.rule.rileResource/282) wt.util.WTException: Exception is generated due to value to long. See details below:
A Cabinet member must be assigned to a cabinet, not a subfolder.
OIR folder rule is to put the Change Notices in: default/change/change notice/2016
We use the same structure for change requests and promotion requests and they c go to the proper folder.
I am in all roles on the system and the system admin, so I can't see what permission I am missing.
Windchill 10.0 m040
Ben
Solved! Go to Solution.
Hi Ben,
This looks to be similar to issue documented in solution https://support.ptc.com/appserver/cs/view/solution.jsp?n=CS128068
Regards,