cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
Showing results for 
Search instead for 
Did you mean: 

Community Tip - Learn all about the Community Ranking System, a fun gamification element of the PTC Community. X

Cannot add resulting objects to change task

BrianToussaint
19-Tanzanite

Cannot add resulting objects to change task

I'm on 11.1 m020.  I am trying to set up a change notice to show some users.  Originally the change notice and change activity were not instaniable.  I turned these on.  Now I can create a Notice and a Task, add Affected Objects to the task, but it will not allow for adding Resulting Objects.  Anyone ever run into this?

ACCEPTED SOLUTION

Accepted Solutions

Brian,

 

Can you add Affected Objects?

 

In type manager check if Change Record is instaniable.

My guess is if you had to turn instaniable on for CN and CA you might have to do the same for Change Record.

 

David

View solution in original post

2 REPLIES 2

Brian,

 

Can you add Affected Objects?

 

In type manager check if Change Record is instaniable.

My guess is if you had to turn instaniable on for CN and CA you might have to do the same for Change Record.

 

David

@d_graham that was what it was. Thank you for the tip!

 

Brian

Announcements


Top Tags