Revising EPM Document revisions backwards

bmills
1-Newbie

Revising EPM Document revisions backwards

Designation: Non-SSA/Finmeccanica

Hi everyone,

My current installation is a migration from 3.4 and it was poorly used
as a revision control tool. As a result some of the migrated data has
incorrect revisions and some of these are set higher that they should
be. At a previous company I had some SQL code for Intralink 3.4 that
could "back up" an incorrect revision (01.1 > 00.5 assuming 00.1 through
00.4 exist). Does anyone have/know of a similar technique to change
Windchill revisions or is this a spider web that I don't want to fall
into.



Intralink 9.1 M050 is my current install and the database is Oracle 11g.



Bob Mills

Engineering Software Administrator



DRS Training and Control Systems, LLC

645 Anchors Street

Fort Walton Beach, Florida 32548

850-302-3241

rmills@drs-ds.com <">mailto:rmills@drs-ds.com> www.drs-ds.com