I am working on an upgrade from Windchill10.0 mo40 running on Oracle 11g

I would like to upgrade to Windchill 11.0 m030 running on Oracle 12c.

 

Do I need to do anyjthing special to do this or will the Upgrade Manager handle all of the updates to Windchill and the Oracle schema?

 

ACCEPTED SOLUTION

Accepted Solutions

WinDU tasks for 10.2 is enough.
I upgraded system from 10.1 to 11.0 there the WinDU tasks also only for 10.2.
You must use export/import dump procedurу for oracle.

View solution in original post

3 REPLIES 3

You need to run WinDU tasks for Upgrade preparation.
Export/import oracle database to dump file.

That is a problem with the way PTC has mishandled WinDU!

I have run WinDU for the 10.2 upgrade, but PTC did not release WinDU patches for a 10.0 to 11.0 upgrade.

All of the Upgrade for 10.2 WinDU checks come back with no errors and a few warnings. A complete WinDU run does the same.

 

That is my plan for the database, export from the 11g and import to 12c, then run Upgrade Manager.

WinDU tasks for 10.2 is enough.
I upgraded system from 10.1 to 11.0 there the WinDU tasks also only for 10.2.
You must use export/import dump procedurу for oracle.