A colleague ran across this the other day and I'm really surprised that I have not see this before.
1. Create an explode-state.
2. Show it in a drawing.
3. Create a note with leader attached to an entity in that view
3. Add a component that increases the size of the view boundary
4. The note created in #3 moves
I understand the background of why it moves as the view boundary increases, but I find it completely unacceptable. I'm far from being a software programmer, but it seems easy enough to lock in the leader geometry and the attachment point on the entity. This would keep my note in the same place no matter what the view boundary does.
I submitted it to PTC-support, but their workaround seems only concerned with the origin location of the actual view and not notes associated with it.
Does anybody have a workaround for this?
Note: this is in Creo Elements/Pro 5.0 M170, but I believe it's still in all WF and Creo releases.
-Josh
This thread is inactive and closed by the PTC Community Management Team. If you would like to provide a reply and re-open this thread, please notify the moderator and reference the thread. You may also use "Start a topic" button to ask a new question. Please be sure to include what version of the PTC product you are using so another community member knowledgeable about your version may be able to assist.