如何在process plan 中确定零部件是来自于Mbom中的哪一部分

JW_7580554
6-Contributor

如何在process plan 中确定零部件是来自于Mbom中的哪一部分

在学习创建process plan / work element .

如下图,我该如何查看在左侧的MBOM结构视图中的某个部件,被分配去了process plan中的哪项work element ?

JW_7580554_0-1769168328510.png

 

2 REPLIES 2
Fadel
23-Emerald I
(To:JW_7580554)

Take a look at https://www.ptc.com/en/support/article/CS454485 

we can define an alias attribute on Part to show the consuming Operation 

Fede

Hi @JW_7580554 ,

I wanted to see if you got the help you needed.

If so, please mark the appropriate reply as the Accepted Solution or please feel free to detail in a reply what has helped you and mark it as the Accepted Solution. It will help other members who may have the same question.

Of course, if you have more to share on your issue, please pursue the conversation.

Thanks,


Catalina