Create New Promotion Requests
Version: Windchill 12.1
Use Case: We use a two-stage lifecycle, with prototype (numeric revision) parts being stages In Work (unlocked), Under Review (locked), or Prototype (locked) and production (alpha revision) parts being stages Production Change (unlocked), Under Review (locked), or Released (locked). Prototype parts get promoted to Prototype on promotion requests while production parts get released to Released via change notices. Recently, a production part was on a change notice. It was in the Production Change state so an engineer could complete the CAD work. Another engineer put the part on a promotion request and managed to get it released that way. That caused the change notice to fail near the end when it tried to change state to Released.
Description:
We don't want users to put production parts on promotion requests; we want them to use change notices, instead. Disallowing promotion requests on parts in the Production Release state should accomplish that. How can I disallow promotion requests on Production Release objects?
I thought I could use access control rules to not grant Create permission for Promotion Requests on the Production Change state, but I think the state you choose is for the promotion request, not for the objects on the promotion request.