Skip to main content
10-Marble
August 23, 2024
Solved

How to assign the operation of mfg. process plan in plant structure?

  • August 23, 2024
  • 2 replies
  • 2678 views

Version: Windchill 13.0

 

Use Case: Dear, I just want to build structure including operation on Plant structure tree such as the attached image. How should I do to make this?


Description:

Dear,
I just want to build structure including operation on Plant structure tree such as the attached image.

You can see the plant structure in left and also information was built with "0010" operation.

 

How should I do to make this?

Best answer by DamienL

Hi, @PetrH

 

Many thanks to you.

I understood what you mentioned

My additional critical point is how to make structure in 2nd image.

My main question is how to add " 0010, SUB1_Name~", "0040, Name_0010", " 0050, Name~" such as the below.

I cannot add them into the below Work Center or Workstation?

 

Test Plant

 - 10, Linka

   - 10, KIT Pracovisite

      - Pracoviste

         0010, SUB1_Name

         0040, Name_0010,

         0050, Name

 - 20, Pracoviste

    - 0010, TOP_Name

    - 0020, Name_0020

 

Regards,

 

 

2 replies

16-Pearl
August 23, 2024

Hi,

Your structure does not have the Process Plan object yet. 

Usual hierarchy(Structure) is to have Process Plan > Operations.

The Tools / Work centres are not technically in the structure, but by special relation that goes by "Work Centre allocation".

The Roll up of the work centres are the Assembly lines and finally the Plant itself.

 

Basically, you have 2 different (but inter related) structures, one representing the Plant>WorkCentre>Tool hierarchy

and the other is the Process Plan>Operations. (Operations will have a non-structure link to Work centre, tools, resources, Control Characteristics etc.,)

This is how Windchill's take on the Process plan and Facilities.

 

Cheers

Hari

 

Perhaps the help documentation can be useful.

 

 

 

DamienL10-MarbleAuthor
10-Marble
August 23, 2024

Hi

Did you review attached image?  You can see the operation ā€œ0010 ~~ā€. I believe this is operation from process plan.

 

You can take a look at this feature in the below, especially 11:50 ~. 12:05.

 

https://youtu.be/lzdyIO-kjVA?si=nJZdiqzZNACvLR2h

 

I’d like to know how it is possible.

 

Thx

 

 

 

16-Pearl
August 23, 2024

Hi,

Yes saw the video.

I dont think you actually assemble the "Plant" Structure. In the exact portion of the video , the demo shows "Open in Related Plant". So its a contextualized resulting structure.

The hierarchy is usually PP > OP and the OP are having resources and Work centres. The Work centres parallelly roll up to a Plant.

Did you try to recreate the demo in OOTB system (only the plant portion).

 

Digital Work Instruction is an interesting area , we did a POC to a leading automotive customer in India along with the Thingworx Operator Advisor. 

Let us know.

Cheers

Hari

 

 

DamienL10-MarbleAuthor
10-Marble
August 25, 2024

Hi,

 

I did try to create the plant structure and I could make the below

Plant - Work Center - Work Center - Equipment/Jig

                                                                - Part

But I couldn't make such as the below

Plant - Work Center - Work Station - Operation

                                                                - Workstation

 

I want to configure structure the attachment but I couldn't add the Operation. 0010, Assemble Bracket (might include resource & part).

In the movie I can take a look at whole assemble sequence on Visualization by Playback Actions.

 

But I couldn't configure structure similar with movie and I couldn't play operation such as movie 11:50 ~ 12:05 on Related Plant.

 

Ie, in the movie I can see Process Plan Structure and open "Open in related Plant" .

And then I can see the assemble sequence with Playback Actions icon. But I cannot do this. This is exactly my question.

 

Thanks a lot.