Question

Is it possible to get New Drawing Upload Revision same as latest WTPart revision??

  • November 11, 2017
  • 2 replies
  • 1274 views

Hi,

I'm trying to upload a new drawing for existing part which is already in windchill. Here is there any

way to get the initial drawing revision same as WTPart while uploading drawing for first time..

2 replies

12-Amethyst
November 13, 2017

Potentially, it depends on your REVISE preference settings

 

08-34-09_Preference Management.png

15-Moonstone
November 16, 2017

The preference Allow Override On Create CAD Document set to β€œYes” should allow you to specify the same revision as the Part when initially creating the CAD document for the drawing