MPM Link: how to reuse existing mBOM to create mBOM for new part
Based on the eBOM of a wtPart we created a new view version in the mBOM. The mBOM is restructured and documents, process plans, tooling, etc. are added.
wtPart 123 (Design) ---> wtPart 123 (Manufacturing)
Due to a engineering change affecting Form Fit Function a new wtPart (eBOM) is created.
wtPart 123 (Design) ---> wtPart 345 (Design)
Because the differences in definition are only small we want to reuse the existing mBOM (wtPart 123) to create the mBOM for the new wtPart 345. We spent a lot of time to create the initial mBOM and would like to only apply the differences and not to completely rebuild the mBOM from the mBOM.
wtPart 123 (Manufacturing) ---> wtPart 345 (Manufacturing)
Any one having an efficient way of working to achieve this?