cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
Showing results for 
Search instead for 
Did you mean: 

Community Tip - Learn all about PTC Community Badges. Engage with PTC and see how many you can earn! X

Synch on CA Complete

GregOlson
16-Pearl

Synch on CA Complete

Has anyone else had the issue the resultant objects are not set back to released upon resolution of Change Notice? We see it all the time that the CN will leave objects at under review state.

PTC document:

CS111383

TitleNew revised change notice workflow hangs on “Synch on CA Complete” workflow expression in Windchill PDMLink 10.0
Description
  • New revision of Change Notice workflow loses its synchronization with related Change Activities object
  • After revision the Change Notice workflow cannot be completed
Applies ToWindchill PDMLink 10.0
Cause
Resolution
  • Reported to R&D as SPR 2163673
  • Workaround: Set the sequence on Change Activity creation.

If yes, what did you do to resolve this issue?

Thanks,

Greg

1 REPLY 1

Anyone???

Announcements


Top Tags