cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
Showing results for 
Search instead for 
Did you mean: 

Community Tip - Did you know you can set a signature that will be added to all your posts? Set it here! X

Update a running Project Plan with Automated Tasks: Windchill 10

BrianSullivan
9-Granite

Update a running Project Plan with Automated Tasks: Windchill 10

Hello

We would like to use Automatic Execution against a Project BUT also need to be able to update the Project.


1. Project started in MS Project

2. Imported into ProjectLink

3. Start Project Start Plan

Tasks:
1: An Owner of an Activity needs to be able to Update "Work" Hours however the value is Greyed Out. You can increase Duration but it does not allow increase in hours (by Project manager before or after suspended the plan)

2: Once we suspended the Plan; We could not import a (modified plan) not listed.... We want to use the sync functionality. We were able to import in 9.1.

Our Goal:

1. A Project Plan that Automatically sends out Tasks to Users

2. Ability to Update the Project Plan, added Activities, updating entries, (and to do this in MS Project and Sync the differences)



3. If We make a 9.1 Project Template, I believe that would bring me back to Classic Projectlink in Windchill... Would that be a useful workaround? Would I be able to Suspend and Import the Update Plan to a suspended ProjectLink Plan?





Brian Sullivan

0 REPLIES 0
Top Tags