Hello, i have a question.
After upgrading procedure (upgrademanager) from windchill 11.0 to windchill 12.0, instaed re-run uogrademanager for GoLive, can I only re-import db from production to target and delta Vaults?
(ldap i guess does not change in 2/3 days)
Thanks a lot
Solved! Go to Solution.
No. The upgrade manager does a lot of changes to the database. What you do for the test migration should be well documented so that you know exactly all the steps you need to undertake for the production upgrade. Also to the LDAP, so you should keep a backup of the blank LDAP config to which you add your export from 11.
Here's my list of important steps for a Windchill upgrade. Some of the steps are version dependent. You should follow this (or a similar) list for both your test and production upgrade runs.
Windchill upgrade steps (for a Windchill on Oracle with Creo environment - Similar steps for SQLServer and other CAD)
Final upgrade steps
Additional system upgrade steps
No. The upgrade manager does a lot of changes to the database. What you do for the test migration should be well documented so that you know exactly all the steps you need to undertake for the production upgrade. Also to the LDAP, so you should keep a backup of the blank LDAP config to which you add your export from 11.
Here's my list of important steps for a Windchill upgrade. Some of the steps are version dependent. You should follow this (or a similar) list for both your test and production upgrade runs.
Windchill upgrade steps (for a Windchill on Oracle with Creo environment - Similar steps for SQLServer and other CAD)
Final upgrade steps
Additional system upgrade steps