Hi Team,
Need support/clarification on the following use case:
When a Test Run is created from Test Case V2, the Test Run captures and stores that specific version (V2) of the test case. In a scenario where the Test Case is later updated to V3, the Test Run still continues to reference V2 and does not automatically reflect the updated version.
Could you please confirm

Whether there is any way to synchronize or update the Test Case version within an existing Test Run, or
If this behavior is expected by design, what is the recommended best practice to manage this use case?


Please refer support Case Details - 18068685 for more information 

1 reply

BKampling_SAI
13-Aquamarine
July 1, 2026

@SY_10545985 once a test run is created, it is locked into the version of the test case at the time of creation. Ideally, you should not be creating test runs until your test cases are finalized. What is your use case for needing to create test runs while test cases are still being created?