Skip to main content
7-Bedrock
December 24, 2022
Solved

Share files between Prime 7 and Prime 8

  • December 24, 2022
  • 1 reply
  • 1142 views

I have my own versions of Prime 7 and Prime 8.  My company uses Prime 7.  Is there any way to take the Prime 8 files that I created and convert them to Prime 7?

Best answer by LucMeekes

Open the file in Prime 8, Copy all regions into a single area. Close the area.

Start Prime 7 on the same PC. Copy the area in Prime 8 and paste it into the empty sheet of Prime 7.

Save the file from Prime to a different name.

Copy all regions out of the area. Remove the area and save the file from Prime 7 again.

 

Be aware that during any of the steps Prime 7 may crash. If that occurs you could copy one or a few regions at a time...

If your Prime 8 file already contains areas, you'll just have to create area(s) for any sets of regions in between them, since you cannot embed an area into a area.

 

Success!

Luc

1 reply

LucMeekes23-Emerald IVAnswer
23-Emerald IV
December 25, 2022

Open the file in Prime 8, Copy all regions into a single area. Close the area.

Start Prime 7 on the same PC. Copy the area in Prime 8 and paste it into the empty sheet of Prime 7.

Save the file from Prime to a different name.

Copy all regions out of the area. Remove the area and save the file from Prime 7 again.

 

Be aware that during any of the steps Prime 7 may crash. If that occurs you could copy one or a few regions at a time...

If your Prime 8 file already contains areas, you'll just have to create area(s) for any sets of regions in between them, since you cannot embed an area into a area.

 

Success!

Luc

gshockxcc7-BedrockAuthor
7-Bedrock
January 1, 2023

Luc, 

Sorry for the delay in replying.   This seems to be the only viable workaround.

Thank you.