My task table is filled with many resolved tasks.

Sandy7
8-Gravel

My task table is filled with many resolved tasks.

Hello,

 

i see there are many tasks floating into my "My Task" table in windchill. 

Some are engineering change notice and some are deviation which are resolved long ago but still i can see them in my "My Task" window.

how can i clear it ?

WC version 12.0

 

Br,

Sandeep

1 ACCEPTED SOLUTION

Accepted Solutions
HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 ,

Try to change the view to Open

HelesicPetr_0-1701357575236.png

 

You should see just the active tasks then.

PetrH

View solution in original post

2 REPLIES 2
HelesicPetr
21-Topaz II
(To:Sandy7)

Hi @Sandy7 ,

Try to change the view to Open

HelesicPetr_0-1701357575236.png

 

You should see just the active tasks then.

PetrH

is that simple???? Omg, My team finds this funny, they all were over my shoulder trying to understand. 

 

thank you so much @HelesicPetr 