Question

Automatically start Change Activity sub-type

  • June 25, 2015
  • 2 replies
  • 1085 views

I'm looking for a way to have my Change Notice workflow automatically fire off a Change Activity sub-type at a certain point in the workflow.

 

It doesn't feel that outlandish when I walk through it. Is this even remotely possible?

 

It's pretty easy to manually create multiple change activities with different sub-types within a single Change Notice but I'm trying to streamline as much as I can.

2 replies

16-Pearl
June 30, 2015

Hi Don,

If you are looking to start the Change Activity process at certain point in the Change notice workflow you can use Synch Robot. On the other hand, if you want to create Change Activity objects on the fly, that would require customize expression.

Regards,

Bhushan

12-Amethyst
July 1, 2015

Ok. Thanks.