Solved
BOM Transformer Synchronization issue between Design and Engineering view
I am using Windchill PDMLink Release 12.0 and Datecode with CPS 12.0.0.0
When a Change notice is created with the Workflow, The change task includes both Design view and Engineering view of a WTPart, along with associated CAD and Drawing as Affected/Resulting objects, The Design View and Engineering View have Equivalent Links when routed to the Change Activity task, Upon reaching the Change Activity task, the Data Assurance Team checks out the associated drawing and updates the title block and revision block with users names and dates, When checking out the drawing, it causes the Design View to iterate and creates an equivalency mismatch between the Design View and Engineering View. Users then have to resolve the discrepancies in BOM Transformer to synchronize the Design view with the Engineering view.
So can we do any customization on linking/Synchronization the Design and Engineering view in the BOM Transformer
When a Change notice is created with the Workflow, The change task includes both Design view and Engineering view of a WTPart, along with associated CAD and Drawing as Affected/Resulting objects, The Design View and Engineering View have Equivalent Links when routed to the Change Activity task, Upon reaching the Change Activity task, the Data Assurance Team checks out the associated drawing and updates the title block and revision block with users names and dates, When checking out the drawing, it causes the Design View to iterate and creates an equivalency mismatch between the Design View and Engineering View. Users then have to resolve the discrepancies in BOM Transformer to synchronize the Design view with the Engineering view.
So can we do any customization on linking/Synchronization the Design and Engineering view in the BOM Transformer