When using the OOTB customize option to edit the My Tasks table view I can't find the column for priority. Since every tasks have priority I need to show that as a column.But I can't seem to add the column for priority to the table view.Someone help me out in this.

LoriSoodAnswer
23-Emerald II
March 13, 2015

Vino,

You should be able to modify the existing table view or create a new one and add the Priority column to it OOTB. Please let me know if that answers your question.

3-13-2015 5-09-44 PM.jpg

2 replies

ShirishMorkhade
16-Pearl
February 18, 2015

This can be possible with light customization (Data Utility). I remember, I had done it before. Obviously it was another attribute, but I am sure it should not be a big deal for Priority attribute.

Translate
LoriSood23-Emerald IIAnswer
23-Emerald II
March 13, 2015

Vino,

You should be able to modify the existing table view or create a new one and add the Priority column to it OOTB. Please let me know if that answers your question.