I was trying to create a report where I obtain all the stuck CN, where all the existing open task is completed and still the CN is in implementation or not resolved state

I was trying to create a report where I obtain all the stuck CN, where all the existing open task is completed and still the CN is in implementation or not resolved state. I have exported and attached the zip file for the report template for reference. using this report I was trying to fetch all the CNs which is having completed tasks and the CN is not yet resolved or canceled. However, even if I am getting the desired results, I am getting CN’s which is having failed/aborted queues and stuck CN , CN which is in running state for a long time, which is still showing as running in one of the sync robot. Those kind of results I am getting. Even the report has to be optimized. I am getting multiple rows in the report for a single CN, some CN in the report is having open tasks which needs to be completed. Where I wanted to have report with the CN’s where all the existing tasks has been closed/ completed, new task is not generated and the CN is not resolved yet. Also, the generated report does not have an information icon near the CN number, which is very much required. How to get this.

MarcoTosin
21-Topaz II

For information on how to get the info icon, you can read this article.

 

How to add a hyperlink of an object in the query builder report result in Windchill PDMLink

 

Check to see if this is what you're asking for, and then let's move on to the other questions, perhaps formatted a little better, because the way they're written above makes them hard to understand.

 

 

Marco

5 replies

MarcoTosin
21-Topaz II

For information on how to get the info icon, you can read this article.

 

How to add a hyperlink of an object in the query builder report result in Windchill PDMLink

 

Check to see if this is what you're asking for, and then let's move on to the other questions, perhaps formatted a little better, because the way they're written above makes them hard to understand.

 

 

Translate
Marco
4-Participant

Hi Marco,

Thank you so much for the information, it works for the information icon to be appeared in the report.

I was trying to create a report with the following objectives:

  1. To identify all the stuck CN’s in the system - Some of the CN’s are stuck where the synchronisation robo is still in running state with no open tasks which needs to be completed.
  2. CN’s which got stuck due to some failed or long standing queues.

I was trying to obtain the CN’s with the above issues.

I will attach few screenshots related to the report which I have created:

I wanted to understand the following:

  1. what I am doing wrong?
  2. Is there a way to obtain all the kind of stuck CN’s from the system?
  3. My report is is showing some CN’s which is still having open tasks, where my objective is to fetch all the CN’s which are not having any open tasks and also not resolved or cancelled.
  4. Could you please let me know if there is a better way to create a report which satisfies the objectives which I have mentioned?
Translate
MarcoTosin
21-Topaz II

Speaking of stack tasks, take a look at this article.

 

QML report to display pending work items

 

Please note that it states that it is NOT possible to use the same report to retrieve both completed items and those still to be completed.

 

 

 

Translate
Marco
4-Participant

Hi Marco, 

 

Thank you for the information. 

I think a clarification needs to be made from my side. I don’t need the CN tasks which are completed and yet to be completed. I need to obtain the CN’s for which all the tasks are completed (No more open task exists) and the CN is still not moved to Resolved or Canceled state.

Attached documents contains one example CN where no open is available and the CN is not yet moved to resolved state.

 

Thanks & Regards,

Rahul M

Translate
MarcoTosin
21-Topaz II

Have you tried editing the report attached to the article I posted above?

 

You can also work on the report attached to this other article by simply changing the statuses

 

Query Builder Report to fetch list of Change notices for which state is resolved however, resolution date is blank

 

 