Skip to main content
1-Visitor
March 7, 2017
Question

If we go for a change request, will it change the phase of Life Cycle

  • March 7, 2017
  • 1 reply
  • 759 views

If we go for a change request, will it change the phase of Life Cycle

if yes, please give example

if no, please explain why it is like that?

1 reply

23-Emerald III
March 7, 2017

No

Life cycle should not be changing at the Change Request submittal time. The CR has done nothing to change the documents involved, only creates an intention to change the documents. Once the CR has been approved and a change task assigned, then the person assigned the task will revise the documents required. The revise process should bump the revision and change the lifecycle from released to one that the person can work on the parts with.