Is there any way to get the history of standard time of operation from Process plan ?

  • January 24, 2025
  • 1 reply
  • 425 views

Is there any way to get the history of standard time of operation from Process plan ? 
- can we get the history of standard time of operation when it changed. 

Best answer by HelesicPetr

Hi @K_Patil 

If the time is changed, then the operation has to be iterated so get all information from all iterations and control the attribute value.

You can do it by a Report Management.

or just go to previous operation iteration and check the attribute value.

PetrH

1 reply

HelesicPetr
22-Sapphire II
22-Sapphire II
January 27, 2025

Hi @K_Patil 

If the time is changed, then the operation has to be iterated so get all information from all iterations and control the attribute value.

You can do it by a Report Management.

or just go to previous operation iteration and check the attribute value.

PetrH

PetrH