Skip to main content
1-Visitor
May 12, 2016
Question

Predecessor Relationships Constraint not working in Plan activites(ProjectLink)

  • May 12, 2016
  • 1 reply
  • 1204 views

 

I am using Windchill ProjectLink 10.2 M030.

 

I have created a project plan which has 5-6 activities, which needs to start after one another.

 

i.e Activity 2 must start on completion of Activity 1 only and Activity 3 to start after completion of activity 2 and so on.

 

Hence in activty 2, I have given the predecessor relationship as "1FS" and in activity 3, "2FS" and so on.

 

But on starting the project, all activities are available at the same time for respective users and activities are not following the reqd sequnce.

 

Activity does not wait for predecessor avtivity to complete.

 

Has anyone faced similar issues while working on ProjectLink? Any help regarding the same would be appreciated.

 

Best regards

Sharath

1 reply

1-Visitor
February 3, 2017

Hi Sharath,

If the project is in manual execution, the predecessor wont work.

I also faced the same issue. I searched in PTC regarding this. As per the article below, it doesnt work

https://support.ptc.com/appserver/cs/view/solution.jsp?n=CS238623&art_lang=en&posno=3&q=predecessor%20not%20working&sour…

Regards,

Logeshwar.J