I am using Windchill ProjectLink Release 12.1 and Datecode with CPS 12.1.2.1

Project plan replacement issue: Post-importing the new MPP file to the project, the “Actual Start date” is not editable in the “Plan”.

Here are the errors that I faced
Multiple dysfunction

1 reply

Community Moderator
November 19, 2025

Hi @MB_10725944

Thank you for reaching out with your question.

To assist you better, could you please provide more details and context regarding your inquiry? Specifically:
 

  1. Could you share the exact steps you followed to import the MPP file?
  2. Are there any warnings in the Method Server logs during the import?
  3. Is this behavior consistent across different browsers or user roles?
  4. Is the ‘Actual Start date’ issue affecting all tasks or only specific ones?

Including screenshots can also be very helpful in understanding your process. This will enhance the likelihood of receiving valuable assistance from other Community members.

You might also find it useful to refer to the guide on how to ask a good question. Additionally, our community champion has shared tips on key points to include when asking a question on the PTC Community.

I hope this information is helpful.

Best Regards,
Vivek N
Community Moderation Team.