Unwanted Drawing Revision
Version: Windchill 11.2
Use Case: I want to roll back a drawing revision.
Description:
Using Creo 10.0.8.0. We created a drawing weeks ago and assigned a number at rev _-. Checked the drawing in but never released it. Engineering decided to change the part number and when I renamed it, the number change was accepted but the rev level seemed to auto-advance to _A without any prompting from me to do so. The only way I can see to get back to rev_- is to delete the drawing and start over. Is there another way to do this? I have this same problem with a couple of other drawings that had been released but not signed off by everyone (so not 'officially' released in my organization) and now there is a part number change required for those drawings that should not necessarily require a revision either. What seems like not so many years ago (to me), this was a drafter level function, pull down tab and you could go backwards if needed. Any ideas? Thanks.